A can do a piece of work in 20 days and B can do it in 12 days,B work for 9 days,in how many days A alone can do the work​

Respuesta :

roseheart889 roseheart889
  • 03-09-2020

Answer: 9

Step-by-step explanation:

Answer Link

Otras preguntas

Your best friend Paul tells you that his father wants to cook Panamanian ceviche, but he is missing one ingredient. How can you ask what he wants? ?Usted prefie
Congress could only request money and had no power to tax; each state made its own money; there was no national court system. Which one of these weaknesses do y
Shannon drove for 540 minutes. If she traveled 65 miles per hour,how many total miles did she travel?
The median for the given set of six ordered data values is 29.5 9 12 25 __ 41 48 What is the missing​ value?
WORTH 100 POINTS need the answers asap first row -x^2 2x^2 (x/2)^2 x^2 x is less than 2 x is greater than 2 x is less than or equal to 2 x is greater than or
Micheal is 4 times as old as Brandon and is also 27 years older than Brandon. How old is Micheal
What do the principles of notice, choice, onward transfer, and access closely apply to?A. PrivacyB. IdentificationC. RetentionD. Classification
There are 93 calories in a small candy bar how many calories are ther in a half dozen small candy bars?
Graph the system of equations on your graph paper to answer the question. {y=−x+4y=x−2 What is the solution for the system of equations? Enter your an
Why do people die?????