Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

How can financial issues affect parenting?
a triangular prism has a height of 12cm. Each triangular face has a base 4cm and height 7cm find the volume of the prism
Help please 1-12 i will give thanks or brainliest
a person's rectangular dog pen for his dog must have an area of 300 square feet also the length must be 40 feet longer than the width find the dimensions of the
help ASAP PLEASE !!!!!!
In a flashback, the author has to a complete the climax of the story B interrupt the present story C introduce additional characters D move the storyli
61 ones× ​10 ​ ​1 ​​ = ?
How do hormones travel throughout our body?
Which of the following defines Homo erectus? a. thinking man c. wise man b. modern man d. upright man
what is 62.80 rounded to the nearsest hundreth